TeraWulf announced a definitive engineering, procurement and construction agreement with Fluor on November 4 for three buildings at its Justified Data Campus in Kentucky. The agreement expands an earlier limited notice to proceed into engineering, procurement, construction, testing and commissioning.

The scope reaches commissioning

The company describes delivery milestones, procurement oversight, open-book cost reporting and performance protections. Guaranteed maximum pricing is being established as engineering and purchasing progress, so a final fixed project price should not be inferred from the announcement.

Cost controls develop with design

The delivery model gives TeraWulf access to external engineering and construction capacity. Coordinating suppliers, skilled labour and commissioning remains central to converting the contracted computing demand into usable infrastructure.

Readiness requires completed systems

Phased ready-for-service completions are expected from late 2027 through the second quarter of 2028. Progress against design, procurement, construction and acceptance milestones will show whether the expanded EPC scope improves schedule and cost predictability.

Image: TeraWulf / source announcement. Used for source-attributed editorial reporting; rights remain with the owner.

Sources & evidence

Sources describe the announcements and evidence available when this analysis was published. Company claims are attributed; plans and trials are not treated as sustained operation.

  1. TeraWulf Secures Google Credit Backstop; Executes Definitive Fluor EPC Agreement ↗